project server training online - resource allocation

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training online - Resource Allocation

project server training online - Resource Allocation

resolvedResolved · Low Priority · Version Standard

Susannah has attended:
Excel Intermediate course
Project Intro Intermediate course

Resource Allocation

How do you assign resources to tasks

RE: Resource Allocation

Hi Sussanah

Thank you for your question

The easiest way to assign resources to tasks is to :-

1. Open your GANNT chart
2. Click on WINDOW-SPLIT (This splits the screen and places a synchronised version of the task information form in the bottom half)
3. Select the task you wish to resource
4. In the task information form list the resources you wish to apply
5. Click OK

Regards

Stephen


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.07 secs.