Resource Allocation

How do you assign resources to tasks

RE: Resource Allocation

Hi Sussanah

Thank you for your question

The easiest way to assign resources to tasks is to :-

1. Open your GANNT chart
2. Click on WINDOW-SPLIT (This splits the screen and places a synchronised version of the task information form in the bottom half)
3. Select the task you wish to resource
4. In the task information form list the resources you wish to apply
5. Click OK

Regards

Stephen

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.