project server consultants - Resource Allocation

ResolvedVersion Standard

Sarah has attended:
Project Intro Intermediate course

Resource Allocation

I will work 100% on the project until a certain milestone and then will work only 50%. How can I make that automatic in Project?

RE: Resource Allocation

Hello Sarah,

Thanks for your question.

This is possible but you would need to write a fair amount of VBA code and it would be pretty difficult. The effort is probably not worth the result and your best bet would be simply change your availability at the scheduled time for the milestone, and then attach a note reminding you to cahnge it if the milestone date changed.

Regards

Stephen

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.