project server consultants - Resource Allocation

resolvedResolved · Low Priority · Version Standard

Sarah has attended:
Project Intro Intermediate course

Resource Allocation

I will work 100% on the project until a certain milestone and then will work only 50%. How can I make that automatic in Project?

RE: Resource Allocation

Hello Sarah,

Thanks for your question.

This is possible but you would need to write a fair amount of VBA code and it would be pretty difficult. The effort is probably not worth the result and your best bet would be simply change your availability at the scheduled time for the milestone, and then attach a note reminding you to cahnge it if the milestone date changed.

Regards

Stephen


 