How do I assign a resource to a task?

RE: Microsoft Project

Hi Marie-Clare

Thank you for your question. There are several ways to do this however you may wish to follow this approach.

First split your screen (Window>Split)
Select the task in the top part of the screen
In the lower part of the screen, left hand pane, click and choose your resource - then click OK.

I hope this answered your question - let us know if we can be of further assistance.

kind regards,

Andrew

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.