Adele has attended:
Project Introduction course
Project Intermediate course
Risk
How do I flag potential risks to the project?
RE: Risk
Hi Adele
Thanks for your question. You could run a filter to show you the tasks Project consider critical (click on the "show all tasks" drop down on the tool bar or go to the Project menu and choose filtered for then select critical.
You could also add a flag field and use that to mark tasks as "risk" - right click on a column and choose insert column. From the field list choose flag1 (perhaps setting the title to Risk) and set the flag to yes for those tasks that meet your criteria.
Alternatively you could insert a text field such as text1 and use it to store a value (perhaps 1 to 5) allowing you to prioritise risk per task.
I hope this is helpful - let us know if you have any other questions.
Kind regards,
Andrew