microsoft project 2003 training - Link

ResolvedVersion Standard

Tim has attended:
Project Intro Intermediate course

Link

What is a link?

RE: Link

Tim

A link between tasks determines how the tasks are related, the default link is finish to start, ie when the predecessor ie A finishes, the successorie B can start.