Forum home » Delegate support and help forum » Microsoft Project Training and help » Duration

Duration

resolvedResolved · High Priority · Version 2019

Bella has attended:
Visio Introduction course
Time Management course

Duration

Hi there,

I recently had some MSP training from Ron and had a question to ask on MSP.

At the moment when entering a month into the 'duration' box it does not provide a full month i.e. 01/01/21 - 01/02-21,


Are you able to change this so that a month is a full month?

Thank you,

Bella

RE: Duration

Hi Bella,

Thank you for your question. Because Project doesn't schedule work on weekends as a default, 1 month in Project is actually 4 weeks of working days(20 days). If you want a calendar month, you need to set duration as 22 or 23 days depending on which month you're in. This also assumes that weekends are non-working.

If you need weekends to be working days, you can change this in the Project tab: Change Working Time - Work Weeks - Details. Select Saturday and Sunday, then set the hours the same as for weekdays. You will need to use 30 or 31 days instead of 1 month for duration.
I hope this helps.

Kind regards
Marius Barnard
STL

Thu 12 Nov 2020: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.11 secs.