Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms+project+training - network diagram

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms+project+training - Network diagram

ms+project+training - Network diagram

ResolvedVersion Standard

Richard has attended:
Project Introduction course
Project Intermediate course

Network diagram

What are the main uses of a network diagram?

RE: Network diagram

Richard

Using this view allows the PM to see the logical relationships between tasks easier.

regards

Dave

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.