Can you remind me how to create non working weekends

RE: Microsoft Project 2013

Hi Rufus

Weekends are normally non working time in Project.
If you need to change or check this this go to
Project (tab)
Change Working Time
Click the Work Weeks tab then Details button.
Select Saturday and Sunday
Click Set dates to non working time.

This will make the weekends non working.
Also check that the Options is set correctly
40 hours per week
5 days per week
20 days per month.

Hope that answers your query?

Regards
Doug Dunn
Best STL

Will be marked as resolved in 5 days

Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.05 secs.