Viewing Predecesors and Succesors in split view
I have split a view as I am trying to view predecessors and successors for a task. I am in task form but it is not displaying the predecessors and successors I am used to seeing in split view. Do I need to choose a different form? If so, which one as I have tried all the ones that I thought might be it.
RE: Viewing Predecesors and Succesors in split view
Hi Tara
To change the lower window in split view -
Right click the grey empty area to the bottom right of the screen. Then choose Predecessors & Successors.
The usual view on my version of Project is Resources & Predecessors and it reverts back to that view for new projects.
To change to the Predecessors & Successors view permanently for all new projects select:
File, Options, Advanced
General Options for this project
Choose All New Projects
Hope that helps with your query?
Doug