Natalie has attended:
Project Advanced course
% complete
% complete question
When i go into my plan and mark items as 100% complete i currently can get two issues
1. after saving, and going back into the plan, its back to 0% (we work with project enterprise and wonder if related)
2. Some of my tasks wont allow me to mark as 100% complete, i dont get an error, it just shows at 0%
3. On summary tasks, if i have 10 sub tasks underneath and all but one item is marked as 100% complete, the summary task shows as 0% until they all are marked up at 100%, typically i would expect the summary to roll up the amount underneath and average it out
RE: % complete
Hello Natalie,
Hope you enjoyed your Microsoft Projectr Advanced course with Best STL.
Thank you for your question regarding the % Complete operation not updating the Summary Tasks and also reverting back to 0% after reopening the file.
Project Enterprise uses Project Server to control all project data. You should have someone who controls the server and who should be able to fix this issue for you.
I came across a site which was discussing a similar issue (they were using PWA) and I have provided you with a link to this site:
http://social.technet.microsoft.com/Forums/projectserver/en-US/ec59a574-450b-4391-972b-662c21306999/project-complete-at-100-for-all-tasks-but-is-not-showing-100-in-pwa
Part of their solution was to restart the server and clear the cache. They reopened the file which showed all tasks reset back to 0% complete. They then changed tasks back to 100% complete and published. The Summary Tasks then showed as 100% complete.
I hope this resolves your question. If it has, please mark this question as resolved and let me know.
If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?
Have a great day.
Regards,
Rodney
Microsoft Office Specialist Trainer