Can you cost project tasks without resourcing first?
RE: Costing
Hi Ruth,
Thank you for your question and welcome to the forum.
You can assign a cost to a task without resourcing. If you apply the Cost table to the Gantt Chart view and then add a value in the Fixed Cost column alongside that task.
I hope this answers your questions.
Regards
Simon