Can you cost project tasks without resourcing first?

RE: Costing

Hi Ruth,

Thank you for your question and welcome to the forum.

You can assign a cost to a task without resourcing. If you apply the Cost table to the Gantt Chart view and then add a value in the Fixed Cost column alongside that task.

I hope this answers your questions.

Regards

Simon

Mon 3 Dec 2012: Automatically marked as resolved.

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.