Forum home » Delegate support and help forum » Microsoft Project Training and help » % Complete changes to 100% when I type in 75%

% Complete changes to 100% when I type in 75%

ResolvedVersion 2007

Nicola has attended:
Project Management - Framework & Processes course

% Complete changes to 100% when I type in 75%

I have a few sub tasks that when I try to update the % Complete field to 50% or more it automatically changes to 100%.

It will let me change to 25% but when I update to 50% or 75% it automatically changes to 100%

I have tried updating in the Update Task box but the same thing happens. I have also been in the Update Project box and ensured it is set for updates between 0% and 100%

The majority of tasks update correctly, so I can't explain why a few of them won't.

Please can you help.

RE: % Complete changes to 100% when I type in 75%

Hi Nicola,

Thank you for your question.

Is it possible to send me the Project file?

If so can you send it to sk@stl-training.co.uk

Regards

Simon

RE: % Complete changes to 100% when I type in 75%

Hi Nicola,

Thank you for the Project.

I believe your problem is that fact you are using Start to Finish relationships rather than Finish to Start relationships.

So perhas a fix you could try is to take a copy of the project and change the relationships from SF to FS.

Are the tasks in the logical order they should happen?

Regards

Simon

Will be marked as resolved in 5 days

Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.

Wed 27 Apr 2011: Automatically marked as resolved.

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.