resource overallocation

Forum home » Delegate support and help forum » Microsoft Project Training and help » Resource Overallocation

Resource Overallocation

resolvedResolved · Urgent Priority · Version 2003

Joanne has attended:
Project Intro Intermediate course
Project Advanced course

Resource Overallocation

I am re-hashing a large and complicated project and have started by programming in recurring meetings. I have set these up successfully and allocated the appropriate resources. The first problem I encountered was some resources showing as over allocated if meetings fell on the same day even though they may only constitute 2 or 3 hrs in an 8 hr working day. I overcame this problem by linking the meetings that occur on the same day finish to start.
I will though also need to allocate these resources to other tasks which will inevitably span at least one meeting and will also possibly overlap with other tasks. These cannot be linked as they need to overlap.
I have tried a test case where I allocated one resource a 15 hr task for which I have allowed him the whole of March to complete. This takes up 8% of his units and project has automatically programmed him to work 1.18 hrs a day to complete it but on the days he also has meetings he is showing as over allocated even though he is well under his daily working hours. How do I prevent this? Is there a way of running concurrent tasks without a resource showing as over allocated until he exceeds his 8 hrs a day?

RE: Resource Overallocation

Hello Joanne,

Hope you enjoyed your Microsoft Project courses with Best STL.

Thank you for your question regarding handling overallocations of resources. It is always very tricky to overcome the resulting overallocations arising from inserting recurring tasks which also have resources assigned to them.

The only way I know of to remove the red overallocated items is by changing the Max. Units in the resource sheet for each resource that is highlighted in red. Doing this does not seem to affect current durations, work or costs. Try increasing the Max. units ten digits at a time until the overallocation disappears. I can't say that this is the best method... try it first. I cannot think of any other way at this point to fix this issue.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Mon 21 Mar 2011: Automatically marked as resolved.


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.