Lag time

what is a lag time?

Edited on Wed 4 Apr 2007, 16:45

RE: lag time

Hi Aimee

Lag is a delay - expressed in units such as days or as a percentage - between two tasks that share a dependency.

Hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.