Is there any function in Project to keep a daily log?
RE: Daily Log
Hi Sharon,
Thanks for the question
You can view your project's budgeted costs and actual costs on a daily basis
On the View menu, click Task Usage.
On the View menu, point to Table, and then click Cost.
On the Format menu, click Detail Styles, and then click the Usage Details tab.
In the Available fields list, hold down CTRL to select nonadjacent fields, and then click Actual Cost, Baseline Cost, and Cost.
Click Show, and then click OK.
Hope this helps
Tracy