Is there any function in Project to keep a daily log?

RE: Daily Log

Hi Sharon,

Thanks for the question

You can view your project's budgeted costs and actual costs on a daily basis

On the View menu, click Task Usage.
On the View menu, point to Table, and then click Cost.
On the Format menu, click Detail Styles, and then click the Usage Details tab.
In the Available fields list, hold down CTRL to select nonadjacent fields, and then click Actual Cost, Baseline Cost, and Cost.
Click Show, and then click OK.

Hope this helps

Tracy


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.