Forum home » Delegate support and help forum » Microsoft Project Training and help » course ms project - Lag

course ms project - Lag

ResolvedVersion Standard

Kate has attended:
Project Introduction course
Project Intermediate course

Lag

How do I add a lag to a task

RE: Lag

Double click on the arrow on the tasks and the TASK DEPENDENCY box appears select LAG