How do I create a milestone??

A

RE: Milestone

Aisha,

Thanks for the question.

To create a Milestone, enter a zero 0 day in the duration part of the task.

Good luck

Regards, Rich


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips