ms ject

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS ject 2007

MS ject 2007

resolvedResolved · Medium Priority · Version 2007

Trevor has attended:
Project Introduction course
Project Intermediate course

MS ject 2007

Need to take the project plan and be able to split taks out by summary and/or resource and print/email to colleagues

RE: MS ject 2007

Hi Trevor

Thank you for your question. Filters will probably help here. From the Project menu choose Filtered for then choose Using Resource. Once you have chosen the resource name MS Project will only show those tasks that have that resource assigned to them making filtering the chart and making it ready for printing.

I hope this helps do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Server loaded in 0.7 secs.