ms ject

ResolvedVersion 2007

Trevor has attended:
Project Introduction course
Project Intermediate course

MS ject 2007

Need to take the project plan and be able to split taks out by summary and/or resource and print/email to colleagues

RE: MS ject 2007

Hi Trevor

Thank you for your question. Filters will probably help here. From the Project menu choose Filtered for then choose Using Resource. Once you have chosen the resource name MS Project will only show those tasks that have that resource assigned to them making filtering the chart and making it ready for printing.

I hope this helps do let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips