activities tasks

ResolvedVersion 2003

Riaz has attended:
Project Management - Framework & Processes course

Activities, Tasks

How do activities differ from tasks?

RE: Activities, Tasks

Hi Riaz

Thanks for your question.

An Activity (or sometimes "Work Package") is the smallest unit in a Work Breakdown Structure. A general rule of thumb suggests that Actvity durations should be no less than a day which means there are probably many steps or Tasks that make up each Activity. Another way of looking at is to say Tasks are too small to track individually but when added together form discrete Activities on the plan.

I hope this helps. Do let us know if you have any further questions.

Kind regards,
Andrew

Thu 17 Sep 2009: Automatically marked as resolved.

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.12 secs.