ms project training london - Milestone

resolvedResolved · Low Priority · Version Standard

John has attended:
Project Introduction course
Project Intermediate course

Milestone

How do I crate a milestone

RE: Milestone

John

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich


 

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.