michael has attended:
Project Introduction course
Project Intermediate course

Milestone

how do you create a milestone

RE: milestone

Michael

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.