Milestone

how do you create a milestone

RE: milestone

Michael

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)