project training - Milestone

resolvedResolved · Low Priority · Version Standard

Damian has attended:
Project Introduction course
Project Intermediate course

Milestone

How do I create a milestone.

RE: Milestone

Damian

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.