microsoft project involuntarily

AI Training: For Busy Decision Makers & Professionals Book now

Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft project - involuntarily hidden tasks | MS-Project forum

Microsoft project - involuntarily hidden tasks | MS-Project forum

resolvedResolved · Urgent Priority · Version 2003

Bella has attended:
Project Introduction course
Project Intermediate course

Microsoft project - involuntarily hidden tasks

I am in the middle of amending a project plan that I have created.

I pressed a button to delete one task and as well as deleting the task the computer has hidden a number of the subsequent tasks. (The task numbers jump from 12 to 34).

I have tried to highlight these bars and click unhide but nothing happens.

How can I retrieve these tasks that are within my plan?

RE: Microsoft project - involuntarily hidden tasks

Hi Bella

Thank you for your question. It sounds like a filter has been applied. To remove all filters press the F3 button or from the Project menu choose Filtered for > All tasks

Does this reveal the missing tasks?

Kind regards,
Andrew

RE: Microsoft project - involuntarily hidden tasks

Hi Andrew

Thanks very much - this has revealed the tasks

Cheers
Bella


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips


Server loaded in 0.11 secs.