Work level available
when looking to level work is there a way of viewing the max level of 'work' available for allocation so that you can see the variance for levelling?
RE: Work level available
Hi Ben,
Thank you for your question.
If you change the view to Resource Usage and right click over the hours window, choose the Remaining Availabilty and it should add it as a row.
I hope this answers your question.
Regards
Simon