Could you plz send me some more information on the 'Update as scheduled' button ?

Thanks

Narain

RE: Schedule

Hi Narain,

Thank you for your question.

The Update as Scheduled button changes the actual dates of all or selected tasks to match the schedule. So this button is only used if you are sure the tasks were all completed as per the schedule.

If some of the tasks have started or finished later than scheduled, then you need to use the Update Tasks button on the Tracking toolbar.

I hope this answers your question.

Regards

Simon

Thu 9 Apr 2009: Automatically marked as resolved.


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Server loaded in 0.1 secs.