Forum home » Delegate support and help forum » Microsoft Project Training and help » Holiday in Resourse Graph and Resource Usage

Holiday in Resourse Graph and Resource Usage

ResolvedVersion 2003

Holiday in Resourse Graph and Resource Usage

Hi!

My question is if MS Project can show Holidays in the Resource Graph/Usage view when the Holidays are entered in the Resource Pool!?
How can i do that?

Thanks a lot

Stefanie

RE: Holiday in Resourse Graph and Resource Usage

In short, yes they will appear.

The longer answer is you need to make sure you use the "Work" Resource Graph (not Peak Units) and "Show Availability Line".

Hope this helps!
J Black
http://www.pmconnection.com

RE: Holiday in Resourse Graph and Resource Usage

Great - works - thanks!

Stefanie

PS: Your name is not really Jack Black, is it?

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.