Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

resources

ResolvedVersion 2003

Debbie has attended:
Project Introduction course

Resources

How do you show initials rather than full name beside the bars on the GANTT chart

RE: Resources

Hi Debbie

Thank you for your question. To put the initials beside the bars on the Gantt chart try this: From the format menu choose Bar styles. The dialogue box that appears shows the objects that can be formatted with the Task type already selected as it's first in the list. At the bottom of the dialogue box switch from the bar tab to the Text tab. You will see that there are several slots around a bar that can hold data from the database. One is already used (Right) which contains the Resource name field. Click on Resource name and replace it with the Resource initials field. OK out of the dialogue box and take a look at the Chart. You should find the initials of any assigned resources appear beside the bars rather than the full names.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 2 Mar 2009: Automatically marked as resolved.

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips