How do I charge for my time?
RE: MS Project
Hi Steve
Thanks for your question.
If you add a standard rate to a resource in the resource sheet and then assign the resource to a task Project will calculate the rolled up cost of the task. In the Gantt view you can see the cost by inserting the cost field in the table [right click on a column header and choose insert column - then choose the cost field] .
I hope this helps let me know if you have any further questions.
Kind regards,
Andrew