How do I integrate other people's project plans into an overall Programme plan written in Project?

RE: MSProject

Hi Veronica

A quick way to do this is to create a new blank project and from the insert menu choose Project... from here you can browse through to find a file to add to your consolidated project. Repeat to add more projects.

I hope this is helpful - let us know if you have any further questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.13 secs.