How do I intepret the "critical path"?

RE: Project

Hi Mark

Thank you for your question. You can quickly see the critical path by looking at the Tracking Gantt view. Tasks coloured red are considered critical by the software. Critical tasks are those that are controlling the end date of the project and have no slack or float around them. This means that if something changes in the duration of a red task then the end date of the project will also change (positively or negatively).

Kind regards,
Andrew

RE: Project

Thank you

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips