formatting

ResolvedVersion 2003

Marianna has attended:
Project Introduction course

Formatting

How do I draw vertical lines?

RE: Formatting

Hi Marianna

Thanks for your question. The vertical lines in the Gantt chart are created by going to Format > Gridlines and from the list choosing Bottom tier column. Change the Type drop down from blank to one of the line types available and click OK.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Wed 10 Dec 2008: Automatically marked as resolved.

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.