Once you have input your tasks can you go back and delete some and insert others- what is the best way to do this

RE: Addition/Deletion of Tasks

Hi Mary

Thanks for your question. You can delete tasks by clicking on the row number to select the whole task row and pressing delete on your keyboard. To insert a new task click on a row and press the insert key on your keyboard. The row will appear immediately above the task you clicked on.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Wed 3 Dec 2008: Automatically marked as resolved.

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.