how can i make red(critical) bars not critical,i done 3 phases the same and project made the last one red(critical)
mark

RE: project

Hi Mark

Project calculates the critical tasks in your project as those that influence the end date of your plan and have no slack or float (that is a change in critical tasks will directly change your end date)

If you'd rather not see the critical path you can work in the Gantt View. By default the critical path is displayed in the Tracking Gantt view.

I hope this helps - let us know if you have any further questions.


Kind regards,
Andrew

Fri 12 Dec 2008: Automatically marked as resolved.

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.