tool bars

ResolvedVersion 2003

Phil has attended:
Project Introduction course

Tool bars

Where has the start date on my tool bar gone?




































RE: Tool bars

Hi Phil

Thanks for your interesting question! It may be that the start column has been removed from the Entry table. To bring it back right click on the finish column header and choose Insert column. Type S for Start, choose the start column and click OK.

I hope this helps. Let us know if you still have problems or if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.