How can I wrap the text of a task in Calendar so that all of the task can be seen without being sent behind another task?

RE: Calendar

Hi Lisa

As far as I'm aware there are no settings to change the row height in Calendar view (View > Calendar) to allow word wrapping. In the Gantt chart (View > Gantt chart) however you can change the row height to allow word wrapping.

Find the task whose name is too long to fit the Task Name column. Move your mouse to the row number for that task and hover the pointer on the row line just below the number.

Left click and drag down. The row height for that task will increase and any hidden text in the row name will wrap into the new space.

I hope this helps. Let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips