Forum home » Delegate support and help forum » Microsoft Project Training and help » 'wrap' text in the calendar view?

'wrap' text in the calendar view?

ResolvedVersion 2007

Rachael has attended:
Project Introduction course

'wrap' text in the calendar view?

How can you 'wrap' text in the calendar view?

RE: 'wrap' text in the calendar view?

Hi Rachael

You can wrap text in the Gantt chart (View > Gantt chart) by changing the row height.

Move your mouse to the row number for the task in question and hover the pointer on the row line just below the number.

Left click and drag down.

Height for that task's row will increase and any hidden text in the row name will wrap into the new space.

I hope this helps. Let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips