Is it possible to represent tolerances in cost or just duration?

RE: Slack

Hi Tom

Thanks for your question - Project will track variances in cost. Once you have a Baseline stored (tools > tracking > save (or set) Baseline then insert a field called Cost Variance. You can insert the field by right clicking on one the columns and from the shortcut menu choose Insert Column.

Hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.21 secs.