David has attended:
Project Introduction course
Project Intermediate course
Project Summary Task
When pasting tasks from an old to a new project, if the Project Summary Task is also copied, upon pasting it becomes a regular task.
Can this be promoted back to a Project Summary Task?
RE: Project Summary Task
Hi David
The project summary task is created for you by Project. As such you won't be able to promote a task to become the summary task. I think your best approach would just be to rename the newly created project summary task and delete the one which became a regular task. Sorry I couldn't help you further. Let us know if you have any other questions.
Kind regards,
Andrew