how do I embed one project into another where the embedded project will not be changed as this will also be embedded into other projects. This effectively will be used as a template
RE: Microsoft Project
Hi Colin
A project file inserted into another plan will update its source file so to be able to bring tasks into a project but have them disconnected from their source file you may find copy and paste a better solution.
I hope this helps - let us know if you have other questions.
Kind regards,
Andrew