how can you create 2 baselines?

RE: project

Hi Juliette

You can create more than one baseline by going to Tools > Tracking > Save Baseline

From the dialog box that appears you can click on the drop down currently saying Baseline and choose one of the other baseline slots to save the data.

Hope this helps. Do let us know if you have other questions.

Kind regards,

Andrew

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.