What's the best way to plan resources who will be working part-time on the project, when they do not work on fixed days each week? Using percentages gets very complicated. Is there a simpler option?
RE: part-time resource
Sorry Jane, but no.
The practical way is to ensure they are in the Resource Sheet as a percentage. Make sure the resource calendar is the Standard calendar. Then after you allocate them to a task, go to Resource Usage view and manually edit the working hours which Project has assigned.