Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

parttime resource

Forum home » Delegate support and help forum » Microsoft Project Training and help » Part-time resource

Part-time resource

ResolvedVersion 2003

Jane has attended:
Project Introduction course
Project Intermediate course

Part-time resource

What's the best way to plan resources who will be working part-time on the project, when they do not work on fixed days each week? Using percentages gets very complicated. Is there a simpler option?

RE: part-time resource

Sorry Jane, but no.

The practical way is to ensure they are in the Resource Sheet as a percentage. Make sure the resource calendar is the Standard calendar. Then after you allocate them to a task, go to Resource Usage view and manually edit the working hours which Project has assigned.

RE: part-time resource

Thanks Alan,

I suspected that was the case!

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.