Forum home » Delegate support and help forum » Microsoft Project Training and help » Getting rid of weekend days on Gantt

Getting rid of weekend days on Gantt

ResolvedVersion 2003

Kathryn has attended:
Project Intro Intermediate course

Getting rid of weekend days on Gantt

I don't want to see Saturdays and Sundays in my Gantt chart. I have amended the working time so that Sat and Sun is non working time and I have changed the formating so non working time should not be shown but it is still showing on the Gantt chart. What am I doing wrong?
Thanks,
Kathryn

RE: Getting rid of weekend days on Gantt

All you can do is use the magnifyinh glasses to change the view to one which does not show Saturdays and Sundays. It is not possible to remove them from the default Gantt view.

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.