Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

levelling out

ResolvedVersion 2003

Carole has attended:
Project Introduction course
Project Introduction course
Project Intermediate course

Levelling out

Please explain what this means: how you would do it and why you would do it.

RE: Levelling out

Hi Carol

Resource levelling is process whereby, at its simplest, work is distributed among resources so that no one resource is exceeding its allocated number of working hours in any period. For example if a resource is working 10 hours in a day, and its resource calendar has it available for only 8, then it would be overallocated and the assignment would require levelling.

There are two main approaches.

First, and recommended, you should solve the overallocations yourself by one or more of the following methods

1.Reassigning another resource to the task
2.Delaying the task to a time when the resource is free
3.Splitting the task, delaying a portion of it to a time when the resource is available
4. Changing the resource's availability so the extra hours are added to its schedule

The second approach is to use the automatic levelling tool. Click on Tools-Levelling-Level resources. Project will then try to resolve the overallocations automatically, by delaying and splitting tasks. There are two problems here.

1.First as it can only delay and split tasks, it is often the case that it can't solve all the problems

2.The levelling tool may well make substantial changes to your project, and the time saved by not solving the problems yourself is often lost spending time refamiliarising yourself with your project.

Hope this is useful

Regards

Stephen

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.22 secs.