Different cost tabs for resource
How do you point plan at a different resource cost tab
RE: Different cost tabs for resource
Hi Carol,
I'm really sorry, as I said that I would show you this during the course and ended up not coming back to it.
Once you have set up a number of different cost tables for a resource within the resource sheet. You then need to select the Resource Usage view. Then select the specific task or group of tasks belonging to a particular resource that you wish to apply a different cost table to. Double click if it's a singluar task, or right click if it's a range of tasks and choose Assignment information. Then select the 'General Tab' and in the bottom right hand corner of this dialogue box you have the ability to select a different cost table.
I hope that answers your query.
Kind regards
Carmen