Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

resource planning

ResolvedVersion Standard

Teri has attended:
Project Intermediate course

Resource Planning

If a resource is over utilised and you adjust the hours to match the available time will Project flag up where this leaves you short of resource and which view is the best place to see this?

RE: Resource Planning

Hello Teri

Thank you for your question

Could you clarify a couple of points for me please?

First, when you say adjust the hours to match the available time do you mean that;

You reduce the hours worked so that the resource can complete the task in the time frame but with less hours worked.

Or

You reduce the duration (in Hours) of the task to match the time available to the resource.

Second, when you say "short of resource" do you mean you want to see the reduction in the hours worked, or the cahnge in task duraton as a result of your changes?

Thanks

Stephen

RE: Resource Planning

Hi Stephen

Thanks for the reply, to clarify, I meant that I reduced the hours worked so that the resource is not required to work more hours than are available. I had selected fixed duration which meant that the duration of the task would not change but that would mean that the task could not then be completed in the time allowed due to insufficient resource. I wanted to know which view to use to see the effect of this change and does Project identify that I don't now have sufficient resource allocated to complete the task in the duration allowed.

Many thanks

Teri

RE: Resource Planning

Hi Teri

If you reduce the number of hours that a resource is working on a task and set the duration to fixed duration, project will recalculate the amount of work on the assumption that the task can now be completed with that amount of work.

For example, if a task has one person working 3 8 hour days then the total amount of work is 24 hours. If you then reduce the hours worked to 12 hours, project will assume that you now mean that it can be completed with that amount of effort.

If that was not the case, then you would have to make up the shortfall, either by increasing the task duration or adding in extra resources.

There is no view that would automatically record this reduction in hours

Regards

Stephen

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.