microsoft-project-training - engineering

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training - Engineering

microsoft-project-training - Engineering

resolvedResolved · Low Priority · Version Standard

Engineering

How to plan a 1 day shutdown with contractors

RE: Engineering

Hi Stephen

Thanks for your question. For a project like this you might initially want to take a look at the templates installed with Project by clicking on File > New and from the Task Pane choosing Templates on my computer. Or if one of those doesn't suit try the link to templates on Office online where you might find a good example that would give you a start in planning this kind of project.

Do let us know if we can of further assistance,

Kind regards,

Andrew


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.05 secs.