microsoft project

Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft Project

Microsoft Project

resolvedResolved · Low Priority · Version Standard

Leeora has attended:
Project Intro Intermediate course

Microsoft Project

Can you link outlook to Microsoft Project?

RE: Microsoft Project

Hi Leonora

Thank you for your question


Could you please clarify for me the sort of things that you are trying to accomplish? In aprticular do you want to import data from Outlook into Project, or export from project to Outlook.

In addition could you give me some idea as to the types of data that you want to work with?

Thankyou

Stephen


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.