RE: Mirosoft Project
Hi Robert
Thanks for your question - now that you have had chance to put your training into practice is there anything you would like help with MS Project?
Kind regards,
Andrew
Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training course - Mirosoft Project
Hi Robert
Thanks for your question - now that you have had chance to put your training into practice is there anything you would like help with MS Project?
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.