Material resource

How do I track a material cost if I want to input my values instead of using % complete? I would like to put in my spent cost values for the material resource. E.G if the fixed cost is

RE: Material resource

Hi Olufemi,

Thank you for your question.

If you are paying for a subcontractor's services at a series of points in the contract and you wish to reflect this, then you could mark those points as milestones in the project and attach fixed costs to those milestones. These costs would then be incurred as you hit them.
Note that in this instance the vendor's resources would have to have zero costs associated with them, otherwise they wiould be double charged.

Regards

Stephen

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.