Forum home » Delegate support and help forum » Microsoft Project Training and help » project courses london - Moving a project date

project courses london - Moving a project date

ResolvedVersion Standard

Paul has attended:
Project Intermediate course

Moving a project date

Moving a complete project without miss placing tasks

RE: Moving a project date

Hi Paul

thanks for your question - you can turn on the analysis toolbar by going to view > toolbars and choosing analysis from the list. The first button the toolbar allows you to adjust your project date. This works best when no work has been assigned to your project.

I hope this helps - do let us know if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips